The four newly built stations of the Minsk Metro in Belarus were opened on 6 November 2020 by President Lukashenko.
The four newly built stations of the Minsk Metro in Belarus were opened on 6 November 2020 by President Lukashenko. Despite the pandemic, we are proud that our SIL4 level Platform Screen Door System, whose design, production and commissioning were successfully carried out by our company, now serves the safety of the people of Belarus.
The design and production processes of the platform screen door systems (PAKS) for the 4 stations on Line 3 of the Minsk Metro began in the first quarter of 2019 by Albayrak Makine Elektronik. Shipment and installation were completed at the end of 2019.
At the beginning of 2020 the Covid-19 outbreak shook the world. Despite the pandemic, with the support and permissions granted by the Governorship of Eskişehir and the Embassy of Belarus in Ankara, our team reached Minsk and we also completed the installation process.